A building contract made final payment conditional on the city inspector's approval. The contractor finished the work and asked the owner to schedule the inspection, but the owner repeatedly refused to allow the inspector onto the property solely to avoid paying. The owner now argues that final payment is not due because there was no inspection approval.
Which statement is most accurate?

Choose the Best Answer